Lesson Learned





By: Giacomo Bonomo

Report No.

6391

Discipline/Origin

Drilling
Own Experience

Well

Gnomoria
35/10-12AS

Date created

2024/06/12
542 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

COSLPromoter

What happened in Surface section:
Not possible to M/U the no-cross joint, because it was not possible to grip with the casing tong on the pup body. Tried to grip on the pup collar, no success.

What Was Planned

Planned to run:
– 13 3/8″ Casing
– 13 3/8″ no-cross coupling
– HPH with 13 3/8″ extension joint
Extension joint below the HPH is M/U as follow:
HPH – 8m 20″ ext joint – XO to 13 3/8″ – 4m 13 3/8″ pup – 1m 13 3/8″ saver pup

What Was Learned

The planned 13 3/8″ pups assy was 5 m (4 +1 m), but actual length of the assy was 4,67 m.
The swab on the no-cross coupling box is +/- 12,5 “, so longer than a standard coupling. The extra length did not allow for enough space to grab on the pup body with the casing tong.

What Actions Are Required

Ensure with casing provider that length of the saver pup is exactly 1 m if the no-cross coupling is planned to be used.

What Was Done

Decided to drop the no-cross coupling and swapped it with a standard joint.